Assessment of implementation timelines
Design engineer Andrii Koretskyi emphasised that building a tunnel under the Dnipro in Kyiv in the coming years is impossible. According to his calculations, the works will take at least five years, and this forecast does not account for risks associated with possible strikes and their consequences.
Design and manufacturing stages
The expert explained that first and foremost, it is necessary to determine the optimal location for the facility, collect the full volume of data, and develop a detailed project. This preparatory stage alone will take a minimum of a year and a half.
An additional obstacle may be the need for a special tunnel boring machine. Since such equipment is often manufactured individually for a specific project, the production process can significantly delay the overall construction deadlines.
Financing and preliminary estimates
Previously, Minister of Restoration Mykola Kalashnyk estimated the cost of the simplest tunnel variant without a metro at $400-500 million, and the implementation timeline at two to three years. Presidential advisor “Flash” (Beskrestnov) also indicated that the execution of such a project would require several years.
Currently, Ukraine is in negotiations with the European Investment Bank regarding securing $100 million to start the implementation of the project.