Russian intelligence and sabotage units are actively working to identify the locations of cogeneration units in Kyiv. These facilities are designed to supply electricity to the capital's critically important infrastructure. Kyiv City Council member Leonid Yemets stated this threat on 19 November.
According to the politician, the situation with electricity supply in the city remains tense. The main reasons are damage to energy facilities resulting from attacks and Kyiv's dependence on external power sources. Yemets shared details during an interview with the publication "Telegraph", where journalists spoke with members of the Kyiv City Council's Temporary Control Committee. This committee monitors the implementation of the capital's comprehensive energy resilience plan.
Dependence on counterintelligence and air defence
Leonid Yemets emphasised that the stability of the city's life-support systems will directly depend on the success of protecting backup energy capacities.
"The enemy is also not wasting time, and its sabotage and intelligence services are working to identify cogeneration sources. And depending on how our counterintelligence services, air defence, and our repair crews perform, it will determine how quickly water, heat, and electricity will appear in Kyiv's homes," the deputy noted.
Cessation of internal generation and dependence on external resources
According to information from the deputies, internal centralised electricity generation in Kyiv is currently completely halted. Previously, three capital thermal power plants produced approximately 1,300 MW of capacity, while the city's average winter demand is about 2,000 MW.
Kyiv City Council member Zoya Yarosh confirmed that the city is currently not generating electricity at these facilities and is forced to obtain the necessary volume from outside. Meanwhile, Russian troops are striking not only generating facilities but also external power supply channels, creating additional risks for the stability of the energy system.
Leonid Yemets added that backup power sources have already been prepared to support critical infrastructure. Their installation took about two years, and the work was carried out even before the launch of the current resilience plan. However, cogeneration units are not capable of fully replacing large power stations and covering the needs of the entire city.
Zoya Yarosh explained that in the event of an electricity shortage, priority will be given to critical infrastructure facilities. Therefore, the presence of additional backup capacities does not guarantee a reduction in the duration of outages for ordinary residents. If Russian attacks cause new destruction, power supply restrictions may be tightened.
Financial difficulties in implementing the resilience plan
Deputies cite delays in funding the comprehensive energy resilience plan as a separate problem. Leonid Yemets reported that the initial budget of the programme was 60 billion hryvnia. It was later cut in half, but the possibility of returning to the previous level is now being considered again.
The Kyiv City State Administration and the central government agreed on joint financing of projects in a 50-to-50 ratio. However, disagreements arose between the parties regarding the determination of customers, funding volumes, and documentation preparation. Additional complications were caused by the blocking of treasury payments, which delayed the procurement and supply of equipment, including foreign-made items.
Later, part of the funding was restored. On 9 October, the state unblocked payments for specific Kyiv energy resilience projects. These concerned backup heat supply, cogeneration stations, and ensuring uninterrupted power supply to water utility facilities.
In accordance with the plan, during 2026, the capital was scheduled to create 1,600 MW of backup heat supply and 40 MW of backup power supply for water utility facilities.
The role of cogeneration and future challenges
Cogeneration units allow for the simultaneous production of electricity and heat. Such facilities can ensure the autonomous operation of individual life-support systems even in the event of disruptions in the centralised network. However, their capacity is insufficient to fully meet the needs of a multi-million-strong city.
Therefore, the stability of electricity, heat, and water supply in Kyiv in winter will depend not only on the availability of backup energy sources but also on the effectiveness of air defence, the protection of energy facilities, and the speed of restoring damaged infrastructure.
It is worth noting that previously, law enforcement officers conducted searches at "Kyivteploenergo", seizing documents related to the capital's energy resilience projects. The enterprise stated that investigative actions could complicate the implementation of important energy projects.